Primary Sludge Volume Calculator

Primary Sludge Volume Calculator

Primary sludge pumping is sized on wet volume, but the solids come from the TSS removed. Convert between dry pounds and pumpable gallons here.







Primary Sludge
Item Value

How the calculation works

Formulas
TSS removed (mg/L) = influent TSS − effluent TSS
Dry solids (lb/day) = 8.34 × flow (MGD) × TSS removed (mg/L)
Wet sludge (gal/day) = dry solids (lb/day) ÷ (8.34 × specific gravity × solids fraction)
Pump rate (gpm) = wet sludge (gal/day) ÷ 1,440

Notes & limitations

The 8.34 lb/gal conversion and the dry-to-wet volume relation are standard (Metcalf & Eddy; WEF MOP 8). Percent solids is the dominant variable — a 1-point change in % solids changes the pump volume by roughly 25%.
  • Verify % solids with lab total-solids testing; hopper sludge is often thicker than the pumped average.
  • Size pumps and piping for the peak-day sludge blanket, not the average — add capacity for scum and washdown solids.
  • This covers primary sludge only; add waste activated sludge and chemical sludge separately for the total to digestion or dewatering.